Maintenance works after concrete batch mixing plant turn off
Follows maintenance works shall be done after concrete batching plant shut off:
1, After the operation, should clean up the mixing drum, discharging gate and the hopper, and rinse with water, at the same time, washing additives and feed system. Knife support, knife-edge of weighing system should be cleaned, and should ensure the weighing accuracy.
2, Exhaust the water of pumps in freezing season, additives, pumps, tanks and additives tank, and should start the pumps and additives pump running a minute or two.
3, When the batching plant transfer or outage, should clean the tank, additive tank, cement, sand, stone storage hopper and weighing hopper. In the transferring process, the sensor should be unloaded.
We hope that these instructions can bring you help. As a professional manufacturer of concrete batching plant, we sincerely hope that our products can bring you more convenience and save more investment.
If you have the need of the concrete mixing plant, welcome to contact us freely.